Town of Palm Beach Marina Construction remains on schedule with the following highlights for the month of August:
- Marina excavation and fill disposal at Tarpon Cove is nearly complete
- Brazilian Building exterior is complete and floors have been installed
- Concrete cap and facings are near completion
- Palm Way Dock utilities are installed with power pedestals and switch cabinets placed on the docks
- Brazilian Dock utilities remain in progress and power pedestals and switch cabinets are being placed on the docks
- Australian Dock delivery is complete along with the main gangway. Power pedestals and switch cabinets installation is nearing completion
- Peruvian Dock deliveries are complete and the dock is being assembled
- Upland electrical conduit work continues
- Peruvian Building vertical construction is complete
- Lake Drive Park improvement project is well underway with sidewalks and curbing installation ongoing
- Paver installation for the Lake Trail and paths are nearly complete
- Landscape material is in the process of being installed